Working
in conjunction with
|
|

ASSET
MANAGEMENT REFURBISHMENT -------------------------------------------------------------------------------------------- Deutsche
Office Trust, 1 Margaret Street, SYDNEY
|

|
|

|
MAIN
CONTRACTOR: JOHN
HOLLAND CONSTRUCTIONS Project
Manager: Mr Peter Fulton Foreman:
Mr Paul Cassel RICE DAUBNEY:
Mr Tony Fabro / Steve Rouge
INSTALLATION
AREA OF TOPPING: 20,000
mē
|
|
Deutsche
Office Trust referred ALLSEAL to the Builder
John Holland Constructions as their preferred
contractor for the rectification of floor
areas. As there were 80mm deflections between
columns and skirting, Allseal surveyed the
floor and offered a cost effective solution
to aesthetically improve the levels whilst
maintaining engineering constraints. The
total 20,000mē was installed by Putzmiester
pump within a time restraint of 5 weeks.
|
|
|